Convincing Features
School
*We aren't endorsed by this school
Assignment Type
Subject
Uploaded by Malaysia Assignment Help
Date
Popular Talent Co. is planning to find new talents among teenagers. They have decided to organize a singing competition called ‘Rising Star Competition 2025’ for teenagers between 15 to 18 years old in Klang Valley. The event will be held on 31st May 2025. They will be awarded RM10,000, RM5,000, and RM2,500 for the 1st, 2nd, and 3rd place respectively. You have been appointed as Project Manager and are responsible for organizing this event successfully.
As a Project Manager, the company wants you to make this competition interesting and may attract powerful talent. Below are the tasks that need to be completed before the events. To assist further, kindly use Microsoft Project 2019 in entering and tracking the tasks to ensure the event runs smoothly. Create a project named Rising Star Competition 2025.
Venue
Promotion
Facilities and Equipment
Participants
Refreshment
Prize Award
Rise Star Competition Day (milestone)
The tasks need to be set as Auto Scheduled, and all task dependencies are Finish-to-Start (FS).
Screenshot the standard calendar.
1. Assign resources as the table below. Change YOURNAME into your own name. Screenshot the Resource Sheet.
1.) Assign resources as below. Display the name of the resources on the right of the bar in the Gantt chart. Screenshot the Resource Usage View.
a). Kayreen – 2, 8, 11, 20
b). Helena – 6, 9, 12, 14, 19
c). Mikhael – 4, 8, 14, 18, 20
d). Aralyn – 3, 11, 15, 22
e). YOURNAME – 7, 9, 12, 16, 23
2.) Change the standard cost rate table as below. Screenshot the Resource Sheet view. (5 marks)
a). Mikhael – RM200/hr.
b). Kayreen – RM180/hr.
c). Helena – RM120/hr.
d). Aralyn – RM150/hr.
e). YOURNAME – RM130/hr.
4.) Screenshot the whole Gantt chart. View the Resource Name at the right side of the gantt bar.
1.) Update the new Status date as 13/09/2024. Screenshot the Project Information dialog box.
2.) Use the options in Update Project dialog box to record that work has been completed as scheduled through 21/04/2025. Screenshot the Task Sheet.
3.) Choose task 14 (List all participants) and click 75% complete. Change into Tracking Table and screenshot the Gantt bar for the task.
4.) Screenshot the whole Gantt chart with Tracking Table (fit to one page).